11..Quickbuild Ltd entered into a two-year contract on 1 Januar y 20X7 at a contract price of...
Question:
11..Quickbuild Ltd entered into a two-year contract on 1 Januar y 20X7 at a contract price of 250,000.
The estimated cost of the contract was 150,000. At the end of the first year the following information was available:
● contract costs incurred totalled 70,000
● inventories still unused at the contract site totalled 10,000
● progress payments received totalled 60,000
● other non-contract inventories totalled 185,000.
Required:
(a) Calculate the Income Statement entries for the contract revenue and the contract costs.
(b) Calculate the Balance Sheet entries for the amounts due from construction contracts and inventories.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Financial Accounting And Reporting
ISBN: 9780273712312
12th Edition
Authors: Barry Elliott, Jamie Elliott