Strong Structure Limited was awarded a contract for construction of a flyover by the Government of Delhi

Question:

Strong Structure Limited was awarded a contract for construction of a fly­over by the Government of Delhi on 1st October 2014. The contact consideration was fixed at ₹280 crore. The fly­over was competed on 31st December 2016 with the following details: 

Particulars Cost incurred during the year Estimated cost of work yet to be completed Payment received from

The company uses the percentage of completion method for recording revenue. The stage of completion of project is determined by the proportion that contracts costs incurred for work performed up to the balance sheet date bear to the estimated total contract costs. Show the revenue, cost and profit to be recorded from this contract.