Bartov Corporation agreed to build a warehouse for a client at an agreed contract price of ($
Question:
Bartov Corporation agreed to build a warehouse for a client at an agreed contract price of \(\$ 2,500,000\) Expected (and actual) costs for the warehouse follow: 2007, \$400,000; 2008, \$1,000,000; and 2009. \(\$ 500,000\). The company completed the warehouse in 2009 . Compute revenues, expenses, and income for each year 2007 through 2009 using the percentage-of-completion method.