Budget performance reports for cost centers OBJ. 2 Partially completed budget performance reports for Saskatoon Company, a

Question:

Budget performance reports for cost centers OBJ. 2 Partially completed budget performance reports for Saskatoon Company, a manufacturer of light duty motors, follow:

Saskatoon Company Budget Performance Report—Vice President, Production For the Month Ended June 30, 2016 Plant Budget Actual Over Budget Under Budget Eastern Region $936,000 $933,750 $2,250 Central Region 669,600 666,000 3,600 Western Region (g) (h) (i)

(j) (k) $ (l) $5,850 Saskatoon Company Budget Performance Report—Manager, Western Region Plant For the Month Ended June 30, 2016 Department Budget Actual Over Budget Under Budget Chip Fabrication

(a)

(b) (c)
Electronic Assembly $191,250 $194,040 $ 2,520 Final Assembly 308,250 307,440 $810

(d)

(e) $

(f) $810 Saskatoon Company Budget Performance Report—Supervisor, Chip Fabrication For the Month Ended June 30, 2016 Cost Budget Actual Over Budget Under Budget Factory wages $ 59,940 $ 61,500 $1,560 Materials 156,600 155,520 $1,080 Power and light 8,640 10,260 1,620 Maintenance 15,120 16,560 1,440 $240,300 $243,840 $4,620 $1,080

a. Complete the budget performance reports by determining the correct amounts for the lettered spaces.

b. Compose a memo to Robin Mooney, vice president of production for Saskatoon Company, explaining the performance of the production division for May.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Financial And Managerial Accounting

ISBN: 9781305267831,9781305267848

13th Edition

Authors: Carl S. Warren , James M. Reeve , Jonathan Duchac

Question Posted: