You are given the following data for risk-free return (RF) and expected market return (RM) along with
Question:
● You are given the following data for risk-free return (RF) and expected market return (RM) along with the risk involved in respect of a number of projects:
Project RF (%) RM (%)
E 7.5 13 0.96 F 9.0 16 1.00 G 10.0 20 1.75 What is the required Rate of Return on equity in each project under Capital Asset Pricing Model
(CAPM)? What generalisations can you make?