MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 20X1 and was

Question:

MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 20X1 and was completed in 20X2. Information relating to the contract follows: 

20X1 20X2 Costs incurred during the year Estimated additional cost to complete Billings during the year Cash collections during the year $290,000 145,000 260,000 $150,000 265,000 240,000 285,000


Required:

1. Record the preceding transactions in MSK’s books assuming it recognizes revenue over time and uses costs incurred to measure the extent to which its performance obligation has been satisfied.

2. Record the preceding transactions in MSK’s books assuming it recognizes revenue at a point in time when control of the completed factory is transferred to the customer at the end of the project.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Financial Reporting And Analysis

ISBN: 9781260247848

8th Edition

Authors: Lawrence Revsine, Daniel Collins, Bruce Johnson, Fred Mittelstaedt, Leonard Soffer

Question Posted: