26. You are choosing between two projects, but can only take one. The cash flows for the...
Question:
26. You are choosing between two projects, but can only take one. The cash flows for the projects are given in the following table: 0 2 3 A -$50 B -$100 20 225 240 250 60
a. What are the IRRs of the two projects?
b. If your discount rate is 5%, what are the NPVS of the two projects?
c. Why do IRR and NPV rank the two projects differently?