Question:
12. NPV. A proposed nuclear power plant will cost $2.2 billion to build and then will produce cash flows of $300 million a year for 15 years. After that period (in year 15), it must be decommis- sioned at a cost of $900 million. What is project NPV if the discount rate is 5%? What if it is 18%? (LOI)