Stinnett Transmissions, Inc., has the following estimates for its new gear assembly project: Price = $1,220 per
Question:
Stinnett Transmissions, Inc., has the following estimates for its new gear assembly project: Price = $1,220 per unit; variable costs = $380 per unit; fixed costs = $3.75 million; quantity = 90,000 units. Suppose the company believes all of its estimates are accurate only to within ±15 percent. What values should the company use for the four variables given here when it performs its bestcase scenario analysis? What about the worst-case scenario?