Explain why, if two mumally exclusive projects are being compared, the short-term project might have the higher
Question:
Explain why, if two mumally exclusive projects are being compared, the short-term project might have the higher ranking under the NPV criterion if the cost of capital is high, but the long-term project might be deemed better if the cost of capital is low. Would changes in the cost of capital ever cause a change in the 1RR ranking ot two such projects?