Items P and Q have capacity bills as follows: a. In week 1 there is an MPS

Question:

Items P and Q have capacity bills as follows:image text in transcribed

a. In week 1 there is an MPS quantity of 90 Ps and 75 Qs. In week 2 the MPS quantity calls for 78 Ps and 103 Qs. What are the capacity requirements for each of the work centers for weeks 1 and 2?

b. Each work center has a standard stated capacity of 120 hours per week. If the facility uses infinite capacity planning techniques, what should they do, if anything (be specific)?