7.2 Each unit requires direct labor of 2.2 hours. The labor rate is $11.50 per hour and...
Question:
7.2 Each unit requires direct labor of 2.2 hours. The labor rate is $11.50 per hour and next year’s direct labor budget totals $834,900. How many units are included in the production budget for next year?