What is MajorNets direct labor efficiency variance for August? a. $919.80 F b. $1,071.00 F c. $1,121.40
Question:
What is MajorNet’s direct labor efficiency variance for August?
a. $919.80 F
b. $1,071.00 F
c. $1,121.40 F
d. $3,364.20 F
MajorNet Systems has budgeted three hours of direct labor per connector, at a standard cost of $17 per hour. During August, technicians actually worked 189 hours completing 84 connectors. All 84 connectors actually produced were sold. MajorNet paid the technicians $17.80 per hour.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Horngrens Accounting The Managerial Chapters
ISBN: 9781292105871
11th Global Edition
Authors: Tracie L. Miller-Nobles, Brenda L. Mattison, Ella Mae Matsumura
Question Posted: