=+16-24 K Manufacturing cycle time, manufacturing cycle efficiency (CMA, adapted) OBJECTIVE 2 Bryson Ltd evaluates the performance
Question:
=+16-24 K Manufacturing cycle time, manufacturing cycle efficiency (CMA, adapted) OBJECTIVE 2 Bryson Ltd evaluates the performance of its production managers based on a variety of factors, including cost, quality and cycle time.
The following information relates to the average amount of time needed to complete an order for its one product:
Wait time:
From order being placed to start of production 8 days From start of production to completion 6 days Inspection time 2 days Process time 4 days Move time 2 days Required 1 Calculate the manufacturing cycle efficiency for an order.