=+4 Assume that demand is uniform throughout the year and known with certainty so that there is

Question:

=+4 Assume that demand is uniform throughout the year and known with certainty so that there is no need for safety stocks.

The purchase order lead time is one week. Calculate Landsborough Lawns’s reorder point for the rotor blade part.