Comprehensive variance analysis. Pacific Furniture is an elite desk manufacturer. At the start ofMay 2007, the following
Question:
Comprehensive variance analysis. Pacific Furniture is an elite desk manufacturer. At the start ofMay 2007, the following budgeted unit amounts (based on a standard costing system)
related to its manufacture of executive desks (made out of oak):
Direct materials:
1.6 square metres of oak per desk
$24 per square metre Direct manufacturing labour:
3 hours per desk
$36 per direct manufacturing labour-hour Budgeted production for May 2007 was 700 executive desks. There were no begin¬
ning inventories of direct materials or finished goods on May 1, 2007. Work in
• • • i FLEXIBLE BUDGETS, process is minimal.
Actual results for May 2007 are as follows:
Direct materials purchased (1,264 square metres) $31,094 Direct materials used (1,185 square metres) ?
Direct manufacturing labour (2,325 hours at $37 per hour) ?
Actual production in May 2007 is 750 executive desk units. A constant purchase price for oak wood existed in May 2007.
Required 1. Prepare a detailed flexible-budget variance analysis for May 2007 covering direct materials and direct manufacturing labour.
2. Give two explanations for each of the variances you compute in requirement 1.