31. (Missing data, three-variance approach) The flexible budget formula for total overhead for the Windlass Corporation is

Question:

31. (Missing data, three-variance approach) The flexible budget formula for total overhead for the Windlass Corporation is $720,000  $16 per direct labor hour.

The combined overhead rate is $40 per direct labor hour. The following data have been recorded for the year:

Actual total overhead $1,160,000 Total overhead spending variance $ 32,000 U Volume variance $ 48,000 U Use a three-variance approach to determine the following:

a. Number of standard hours allowed

b. Actual direct labor hours worked

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Cost Accounting Traditions And Innovations

ISBN: 9780324180909

5th Edition

Authors: Jesse T. Barfield, Cecily A. Raiborn, Michael R. Kinney

Question Posted: