1 A supplier of instrument gauge clusters uses a kanban system to control material flow. The gauge...
Question:
1 A supplier of instrument gauge clusters uses a kanban system to control material flow. The gauge cluster housings are transported five at a time. A fabrication center produces approxi- mately 10 gauges per hour. It takes approximately two hours for the housing to be replenished. Due to variations in processing times, management has decided to keep 20 percent of the need- ed inventory as safety stock. How many kanban card sets are needed?