19 Bill Edstrom, managing partner at a biomedical consulting firm, has requested your expert advice in devising

Question:

19 Bill Edstrom, managing partner at a biomedical consulting firm, has requested your expert advice in devising the best schedule for him for the following consulting projects, starting on 2/2/05:

image text in transcribed

The consulting firm charges a flat rate of $4,000 per day. All four firms impose fines for late- ness. Reardon Biotoch charges a $500-per-day fine for each day that the completion of the con- sulting work is past the due date; Vertex Pharmaceuticals, Novartis, and OSI Pharmaceuticals all charge a fine of $1,500 per day for each day late. Prepare alternative schedules based on the following priority rules: SOT, FCFS, EDD, STR, and another rule-longest processing time (LPT), which orders jobs according to longest assigned first, second longest assigned second, and so on. For the sake of simplicity, assume that consulting work is performed seven days a week. Which rule provides Bill with the best schedule? Why?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations Management For Competitive Advantage

ISBN: 1572

11th Edition

Authors: Richard B. Chase, F. Robert Jacobs

Question Posted: