3 A bottling plant fills 2,400 bottles every two hours. The lead time is 40 minutes and...

Question:

3 A bottling plant fills 2,400 bottles every two hours. The lead time is 40 minutes and a container accommodates 120 bottles. The safety stock is 10 percent of expected demand. How many kanban cards are needed?