=+ 3 in the problem above, the operations manager in charge of the process reallocates the work

Question:

=+ 3 in the problem above, the operations manager in charge of the process reallocates the work at each stage to improve the ‘balance’ of the process. now each stage has an average of 64 minutes of work. also, the work-in-progress in front of stages B, C and D is 75, 80 and 82 units respectively. How has this changed the throughput efficiency of the process?