=+ 3 in the problem above, the operations manager in charge of the process reallocates the work
Question:
=+ 3 in the problem above, the operations manager in charge of the process reallocates the work at each stage to improve the ‘balance’ of the process. now each stage has an average of 64 minutes of work. also, the work-in-progress in front of stages B, C and D is 75, 80 and 82 units respectively. How has this changed the throughput efficiency of the process?
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Operations Management
ISBN: 115145
8th Edition
Authors: Nigel Slack , Alistair Brandon Jones , Robert Johnston
Question Posted: