7 An assembly line is to be designed to operate 7 hours per day and supply a...

Question:

7 An assembly line is to be designed to operate 7 hours per day and supply a steady demand of 300 units per day. Here are the tasks and their performance times:

image text in transcribed

a. Draw the precedence diagram.

b. What is the workstation cycle time?

c. What is the theoretical minimum number of workstations?

d. Assign tasks to workstations using the longest operating time.

e. What is the efficiency of your line balance?

f. Suppose demand increases by 10 percent. How would you react to this? Assume that you can operate only 7 hours per day.

Step by Step Answer:

Related Book For  book-img-for-question

Operations Management For Competitive Advantage

ISBN: 1572

11th Edition

Authors: Richard B. Chase, F. Robert Jacobs

Question Posted: