9 The following tasks are to be performed on an assembly line: The workday is seven hours

Question:

9 The following tasks are to be performed on an assembly line:

image text in transcribed

The workday is seven hours long. Demand for completed product is 750 per day.

a. Find the cycle time.

b. What is the theoretical number of workstations?

c. Draw the precedence diagram.

d. Balance the line using sequential restrictions and the longest-operating-time rule.

e. What is the efficiency of the line balanced as ind?

f. Suppose that demand rose from 750 to 800 units per day. What would you do? Show any amounts or calculations. g. Suppose that demand rose from 750 to 1,000 units per day. What would you do? Show any amounts or calculations.