A firm that produces electric golf carts has just received an order for 200 carts, which must be ready for delivery at the start of week 8. Information concerning the product structure, lead times, and quantities on hand is shown in the following table. Use this information to do each of the following:

a. Construct a product tree.

b. Construct an assembly time chart.

c. Develop a material requirements plan that will provide 200 golf carts by week 8, assuming lotfor-

lot ordering.

Parts List for Electric Golf Cart Lead Time Quantity on Hand Electric golf cart 1 0 Top 1 40 Supports (4) 1 200 Cover 1 0 Base 1 20 Motor 2 300 Body 3 50 Frame 1 35 Controls 1 0 Wheel assemblies (4) 1 240 Seats (2) 2 120 LO.1

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations Management

ISBN: 9781260575712

14th Edition

Authors: William J Stevenson

Question Posted: