A machine can operate for an average of 10 weeks before it needs to be overhauled, a

Question:

A machine can operate for an average of 10 weeks before it needs to be overhauled, a process which takes two days. The machine is operated five days a week. Compute the availability of this machine. (Hint: All times must be in the same units.)