A manager is going to purchase new processing equipment and must decide on the number of spare

Question:

A manager is going to purchase new processing equipment and must decide on the number of spare parts to order with the new equipment. The spares cost $200 each, and any unused spares will have an expected salvage value of $50 each. The probability of usage can be described by this distribution:

Number 0 1 2 3 Probability .10 .50 .25 .15 If a part fails and a spare is not available, two days will be needed to obtain a replacement and install it. The cost for idle equipment is $500 per day. What quantity of spares should be ordered?

a. Use the ratio method.

b. Use the tabular method (see Table 12.3). LO.1

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations Management

ISBN: 9781260575712

14th Edition

Authors: William J Stevenson

Question Posted: