An aircraft company has an order to refurbish the interiors of 18 jet aircraft. The work has

Question:

An aircraft company has an order to refurbish the interiors of 18 jet aircraft. The work has a learning curve percentage of 80. On the basis of experience with similar jobs, the industrial engineering department estimates that the first plane will require 300 hours to refurbish. Estimate the amount of time needed to complete

a. the fifth plane.

b. the first 5 planes.

c. all 18 planes.

 LO.1