Consider the following two machines and 6 jobs flow shop problem.

Job Machine 1 Machine 2 1 5 7 2 10 8 3 8 13 4 9 7 5 6 11 6 12 10 Obtain the optimal schedule and the corresponding makespan for the above problem.