Develop a material requirements plan for component H. Lead times for the end item and each component
Question:
Develop a material requirements plan for component H. Lead times for the end item and each component except B are one week. The lead time for B is three weeks. Sixty units of A are needed at the start of week 8. There are currently 15 units of B on hand and 130 of E on hand, and 50 units of H are in production and will be completed by the start of week 2. Lot-for-lot ordering will be used for all items.
A B(2)
D(2) E(2)
C D(2) E(4)
H(3) K H(3) K