Draw the activity-on-node (AON) project network associated with the following activities for Dave Carhart's consult- ing company

Question:

Draw the activity-on-node (AON) project network associated with the following activities for Dave Carhart's consult- ing company project. How long should it take Dave and his team to complete this project? What are the critical path activities? Activity Immediate Predecessor(s) Time (days) a b C d |AABBC D E, F ABCDEFGH 3 4 6 6 4 4 6 8