Refer again to Problems 14.3 and 14.4. In addition to 100 units of S, there is also

Question:

Refer again to Problems 14.3 and 14.4. In addition to 100 units of S, there is also a demand for 20 units of U, which is a component of S. The 20 units of U are needed for maintenance pur- poses. These units are needed in week 6.

Modify the gross material requirements plan to reflect this change. P