The activities described by the following table are given for the Duplaga Corporation: Activity Immediate Predecessor(s) Time

Question:

The activities described by the following table are given for the Duplaga Corporation: Activity Immediate Predecessor(s) Time ABCDERCHL A A D B 9236 B 9 4 G E, F D I G, H 653 3

a) Draw the appropriate AON PERT diagram for Ed Duplaga's management team.

b) Find the critical path.

c) What is the project completion time? P