The first unit of a job took 40 hours to complete. The work has a learning percentage
Question:
The first unit of a job took 40 hours to complete. The work has a learning percentage of 88. The manager wants time estimates for units 2, 3, 4, and 5. Develop those time estimates.
LO.1