The following table contains order-dependent setup times for three jobs. Which processing sequence will minimize the total
Question:
The following table contains order-dependent setup times for three jobs. Which processing sequence will minimize the total setup time?
Following Job’s Setup Time (hrs.)
Setup Time (hrs.) A B C Preceding Job A 2.4 — 1.8 2.2 B 3.2 0.8 — 1.4 C 2.0 2.6 1.3 —