The following tasks must be performed on an assembly line in the sequence and times specified: a.

Question:

The following tasks must be performed on an assembly line in the sequence and times specified:

image text in transcribed

a. Draw the schematic diagram.

b. What is the theoretical minimum number of stations required to meet a forecast demand of 400 units per eight-hour day?

c. Use the longest-task-time rule and balance the line in the minimum number of stations to produce 400 units per day.

Step by Step Answer: