Use graphical method to minimize the needed to process the following jobs on the machines shown (i.e.

Question:

Use graphical method to minimize the needed to process the following jobs on the machines shown

(i.e. for each machine find the job which should be scheduled first). Also, calculate the total time elapsed to complete both jobs.

Job 1 Sequence A - B - C - D - E Time (hrs) 2 6 5 4 7 Job 2 Sequence C - B - D - A - E Time (hrs) 6 5 7 4 8

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations Management

ISBN: 9788122425871

2009 Edition

Authors: Kumar, S. Anil

Question Posted: