King Construction Company began work on a contract in 2019. The contract price is $4,000,000, and King
Question:
King Construction Company began work on a contract in 2019. The contract price is $4,000,000, and King determined that its performance obligation was satisfied over time. Other information relating to the contract is as follows:
................................................................................................2019
Costs incurred during the year .....................................$ 800,000
Estimated costs to complete, December 31 ...............2,400,000
Billings during the year ....................................................600,000
Collections during the year .............................................400,000
Required:
1. How much gross profit or loss does King recognize in 2019?
2. Next Level Prepare the appropriate sections of the 2019 income statement and ending balance sheet.
Step by Step Answer:
Intermediate Accounting Reporting and Analysis
ISBN: 978-1337788281
3rd edition
Authors: James M. Wahlen, Jefferson P. Jones, Donald Pagach