Construction Co. started a contract in June 2017 to build a small foot bridge at a fixed

Question:

Construction Co. started a contract in June 2017 to build a small foot bridge at a fixed price of $10 million. The bridge was to be completed by October 2019 at a total estimated cost of $8 million. Total cumulative costs incurred by the end of December 2017 and 2018 were $2 million and $5.5 million, respectively. Because of cost overruns in 2018, it is now expected that the project will cost $800,000 more than originally estimated. Final costs at the end of the project totalled $9 million. Construction Co. follows the guidance in IFRS. 


Required:

Determine the amount of gross profit to be recognized for the year ended December 31, 2018.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question
Question Posted: