(Gross Profit on Uncompleted Contract) On April 1, 2007, Brad Bridgewater Inc. entered into a cost-plus-fixed-fee contract...

Question:

(Gross Profit on Uncompleted Contract) On April 1, 2007, Brad Bridgewater Inc. entered into a cost-plus-fixed-fee contract to construct an electric generator for Tom Dolan Corporation. At the contract date, Bridgewater estimated that it would take 2 years to complete the project at a cost of $2,000,000.

The fixed fee stipulated in the contract is $450,000. Bridgewater appropriately accounts for this contract under the percentage-of-completion method. During 2007 Bridgewater incurred costs of $700,000 related to the project. The estimated cost at December 31, 2007, to complete the contract is $1,300,000. Dolan was billed $600,000 under the contract.

Instructions Prepare a schedule to compute the amount of gross profit to be recognized by Bridgewater under the contract for the year ended December 31, 2007. Show supporting computations in good form.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Intermediate Accounting 2007 FASB Update Volume 2

ISBN: 9780470128763

12th Edition

Authors: Donald E. Kieso, Jerry J. Weygandt, Terry D. Warfield

Question Posted: