Refer to the situation described in BE 633. Assume that the building was completed during the second
Question:
Refer to the situation described in BE 6–33. Assume that the building was completed during the second year, and construction costs incurred during the second year were $10 million. How much revenue and gross profit or loss will the company recognize in the first and second year if it recognizes revenue upon contract completion?
Data From BE 6-33
A construction company entered into a fixed-price contract to build an office building for $20 million. Construction costs incurred during the first year were $6 million and estimated costs to complete at the end of the year were $9 million. The company recognizes revenue over time according to percentage of completion. How much revenue and gross profit or loss will appear in the company’s income statement in the first year of the contract?
Step by Step Answer:
Intermediate Accounting
ISBN: 978-1260481952
10th edition
Authors: J. David Spiceland, James Sepe, Mark Nelson, Wayne Thomas