Shanahan Construction Company has entered into a non-cancellable contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $600,000 and will take three years to construct. The complex will be billed to the purchasing company at $900,000. The following data pertain to the construction period.
Instructions
a. Using the percentage-of-completion method, calculate the estimated gross profit that would be recognized during each year of the construction period.
b. Using the completed-contract method, calculate the estimated gross profit that would be recognized during each year of the construction period.