The data shown below were gathered while planning a special project. Required: Show your work for the

Question:

The data shown below were gathered while planning a special project.

image text in transcribed

Required:
Show your work for the items below:

a. Draw a network diagram for this project.

b. Identify any critical path.

c. What is the earliest project completion time?

d. Find the slack time for each activity.

e. Discuss possible courses of action if the project must be completed within 40 days.

Step by Step Answer:

Related Book For  book-img-for-question

Internal Auditing: Principles And Techniques

ISBN: 9780894131677

1st Edition

Authors: Richard L. Ratliff, W. Wallace, Walter B. Mcfarland, J. Loeboecke

Question Posted: