Question: 2. Draw a network from the following activities and find a critical path and total duration of project. Activity Duration (Days) Activity Duration (Days) 1-2

2. Draw a network from the following activities and find a critical path and total duration of project.

Activity Duration (Days) Activity Duration (Days) 1-2 4 2-6 18 1-3 7

Activity Duration (Days) Activity Duration (Days) 1-2 4 2-6 18 1-3 7 3-5 10 1-4 10 3-6 16 2-3 3 4-5 9 2-4 8 5-6 6 2-5 11 5-7 11 6-7 8