Question: 7. A project has the following activities Require: i. Critical path and total project duration. ii. Compute earliest event time and latest event time. iii.
7. A project has the following activities

Require:
i. Critical path and total project duration.
ii. Compute earliest event time and latest event time.
iii. Total, free and independent float for each activity.
Activity A B C D E F G H I J K Immediate Predecessors - Duration (Weeks) 3 2247 7 F. G H, I ABBC DEEH 42563