Complete the following input/output report. What are the planned and actual backlogs at the end of period?

Question:

Complete the following input/output report. What are the planned and actual backlogs at the end of period?

3 Total 4 Period Planned Input 39 38 35 36 Actual Input 33 33 40 31 Cumulative Variance


Planned Output 40 40 40 40 Actual Output 38 35 40 38 Cumulative Variance