Question: If in problem 11.15, management said that it is considering increasing the service level to one stockout every 2 years, what would the new safety

If in problem 11.15, management said that it is considering increasing the service level to one stockout every 2 years, what would the new safety stock be? If the cost of carrying inventory on this item is $10 per unit per year, what is the cost of increasing the inventory from one stockout per year to one every 2 years?


In Problem 11.15

Management has stated that it will tolerate one stockout per year. The forecast of annual demand for a particular SKU is 100,000 units, and it is ordered in quantities of 10,000 units. The lead time is 2 weeks. Sales history for the past 10 weeks follows.

Step by Step Solution

3.41 Rating (160 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Sigma 489 units Service 20 120 95 Safety f... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Introduction Materials Management Questions!