If activity C is delayed by two days, the critical path is: (a) not affected. (b) increased
Question:
If activity C is delayed by two days, the critical path is:
(a) not affected.
(b) increased by two days.
(c) possibly increased, depending on slack in subsequent activities.
(d) unable to be determined.