If activity C is delayed by two days, the critical path is: (a) not affected. (b) increased

Question:

If activity C is delayed by two days, the critical path is:

(a) not affected.

(b) increased by two days.

(c) possibly increased, depending on slack in subsequent activities.

(d) unable to be determined.