Budget Variance for Individual Costs. Suzi Greenberg, manager of the Machining Department at Mayfield Industries, Inc. has
Question:
Budget Variance for Individual Costs. Suzi Greenberg, manager of the Machining Department at Mayfield Industries, Inc. has estimated overhead costs for August at an expected operating level of 6,000 machine hours. Past experience indicates a rate of cost variability per hour as follows:
\section*{Required:}
1. Prepare a budget of overhead costs for 5,000 machine hours.
2. Compare the actual overhead costs with the budget for 5,000 machine hours.
Show budget variances for each item.
3. Explain what factors could cause the budget variance to occur.