The departmental supervisor assigned three people with a labor rate per person of ($ 10) an hour

Question:

The departmental supervisor assigned three people with a labor rate per person of \(\$ 10\) an hour to a project with a standard labor rate of \(\$ 9\) an hour. Each person spent 70 hours on this project. What effect will this have on the labor rate variance?