3.16. Complete the following problem. The lead time is one week and the demand time fence is the end of week 3. There are 20 on hand. The lot size is 60.
Period 1
2 3
4 5
6 Forecast 20 21 22 20 28 25 Customer Orders 19 18 20 18 30 22 Projected Available Balance 20 MPS ATP